SOCO-IC-988
120 MW generation in Oglethorpe, GA · In queue since October 2021 · Proposed COD April 2025
120 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-30
SOCO-IC-988 is a proposed solar generation project with a total capacity of 120 MW, located in Oglethorpe County, Georgia. The project is being developed within the Southern Company (SOCO) service area. It entered the SOCO interconnection queue on October 21, 2021, with a proposed commercial operation date of April 30, 2025. Its interconnection agreement (IA) status is currently listed as Suspended.
The point of interconnection (POI) is the East Watkinsville - Russell Dam (USA) 230 kV Line. The project has appeared in recent news coverage regarding renewable energy development in the Southeast region.
Generated from interconnection queue and public data sources
State
GA
County
Oglethorpe
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
East Watkinsville - Russell Dam (USA) 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SOCO-IC-988