SOCO-IC-994
300 MW hybrid in Toombs, GA · In queue since November 2021 · Proposed COD April 2025
300 MW
Capacity
2
Components
Solar + Battery
4y 6m
In Queue
Suspended
IA Status
COD target: 2025
Total Duration
3y 5m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-30
SOCO-IC-994 is a proposed 300 MW hybrid solar and battery project located in Toombs County, Georgia. The development project, located in the Southeast region, consists of 200 MW of solar generation coupled with 100 MW of battery energy storage. The project is being developed within the Southern Company (SOCO) footprint.
The project is currently in the SOCO interconnection queue, with an entry date of November 12, 2021. The proposed commercial operation date is April 30, 2025, and the interconnection agreement status is currently listed as Suspended. The point of interconnection is the Hatch - Vidalia 230 kV Line.
Generated from interconnection queue and public data sources
State
GA
County
Toombs
Grid Region
Southeast
Market
—
Developer
—
Utility
Southern Company
Entity
SOCO
Service Type
—
Point of Interconnection
Hatch - Vidalia 230 kV Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN