Project SOCO-IC-996 — Project Summary

Queue ID
SOCO-IC-996
Capacity
180 MW
Technology
Solar+Battery
Status
active
Location
Charlton, GA
Region
Southeast
Developer
IA Status
Suspended

SOCO-IC-996

SOCO-IC-996BetaActiveSolarBatterySOCOLBNL

180 MW hybrid in Charlton, GA · In queue since November 2021 · Proposed COD February 2026

180 MW

Capacity

2

Components

Solar + Battery

4y 6m

In Queue

Suspended

IA Status

COD target: 2026

Interconnection

Total Duration

4y 3m

Schedule

3 months past proposed COD

In Study38%
Queue EntryNov 23, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-02-01

Technology
Solar120 MW · 67%
Battery60 MW · 33%
About

SOCO-IC-996 is a proposed 180 MW hybrid solar and battery project located in Charlton County, Georgia. The development project, consisting of 120 MW of solar generation and a 60 MW battery energy storage system, is in the Southern Company (SOCO) interconnection queue with an entry date of November 23, 2021. The proposed commercial operation date is February 1, 2026.

The interconnection agreement (IA) status for SOCO-IC-996 is currently listed as Suspended. The point of interconnection (POI) is the Homeland - Macedonia Switching 115 kV Line. The project is listed in the interconnection queue of the Southeast region.

Generated from interconnection queue and public data sources

Project Details

State

GA

County

Charlton

Grid Region

Southeast

Market

Developer

Utility

Southern Company

Entity

SOCO

Service Type

Point of Interconnection

Homeland - Macedonia Switching 115 kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SOCO-IC-996