SPP-ERAS-2025-001
104 MW generation in Lancaster, NE · In queue since September 2025
104 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-ERAS-2025-001 is a proposed generation project located in Lancaster County, Nebraska, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 104 MW, is being developed by Lincoln Electric System (LES). It is a natural gas-fired project utilizing thermal combustion turbine technology.
The project entered the SPP interconnection queue on September 15, 2025. It is currently listed as active in the queue. The point of interconnection (POI) is the 84th & Bluff 115kV Substation. The service type requested is Energy Resource/Network Resource (ER/NR).
Generated from interconnection queue and public data sources
State
NE
County
Lancaster
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
LES
Entity
SPP
Service Type
ER/NR
Point of Interconnection
84th & Bluff 115kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.