SPP-ERAS-2025-002
217 MW generation in Abernathy, TX · In queue since September 2025
217 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-ERAS-2025-002 is a proposed 217 MW gas-fired generation project located in Abernathy County, Texas. The project, utilizing thermal combustion turbine technology, is in the Southwest Power Pool (SPP) interconnection queue under service type ER/NR. Its point of interconnection is the Xcel Tuco 345kV Substation. The queue entry date is September 12, 2025.
The project is currently listed as active in the SPP queue. The utility associated with the project is SPS, and the entity is SPP. There is no proposed commercial operation date or interconnection agreement (IA) status available in the provided data.
Generated from interconnection queue and public data sources
State
TX
County
Abernathy
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Xcel Tuco 345kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-ERAS-2025-002