SPP-ERAS-2025-008
721.1 MW generation in Conway Springs, KS · In queue since September 2025
721.1 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-ERAS-2025-008 is a proposed 721.1 MW gas-fired generation project located in Conway Springs, Kansas. The project, which utilizes combined cycle thermal technology, is being developed within the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-ERAS-2025-008. The project's point of interconnection (POI) is the Viola 345 kV Substation.
The project entered the SPP queue on September 30, 2025, and is currently listed as active, seeking Energy Resource/Network Resource (ER/NR) service type. The utility associated with the project is Western Resources, Inc. (WERE).
Generated from interconnection queue and public data sources
State
KS
County
Conway Springs
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Viola 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Viola Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.