SPP-ERAS-2025-012
750 MW generation in Stanton, ND · In queue since October 2025
750 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-ERAS-2025-012 is a proposed 750 MW natural gas-fired generation project located in Stanton County, North Dakota. The project, utilizing combined cycle technology, is being developed by BEPC and is interconnected within the Southwest Power Pool (SPP) at the Leland Olds 345kV Substation.
The project entered the SPP interconnection queue on October 1, 2025, seeking Energy Resource and Network Resource (ER/NR) service. As of the latest data, the project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
ND
County
Stanton
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
BEPC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Leland Olds 345kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WAUE.BEPM.LOS1
- POI Substation
- 345/230kV Leland Olds Switchyard Addition
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-ERAS-2025-012