SPP-ERAS-2025-016
232.5 MW generation in Earth, TX · In queue since October 2025
232.5 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-ERAS-2025-016 is a proposed 232.5 MW gas-fired generation project located in Earth County, Texas. The project, which utilizes thermal combustion turbine technology, is in the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-ERAS-2025-016. The queue entry date is October 2, 2025. The utility is SPS, and the point of interconnection (POI) is the Tolk 230kV Substation. The project's service type is ER/NR.
The project is currently listed as active in the SPP interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Earth
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Tolk 230kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SPS.TOLK1
- POI Substation
- Tolk Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-ERAS-2025-016