SPP-ERAS-2025-020
400 MW generation in Lovington, NM · In queue since October 2025
400 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed SPP-ERAS-2025-020 project is a 400 MW solar and battery hybrid generation project located in Lovington, New Mexico. Interconnecting to the Southwest Power Pool (SPP) via the Hobbs - Yoakum 345 kV Line, the project entered the SPP interconnection queue on October 2, 2025. It is currently listed as an active project in the queue.
The project is seeking ER/NR service type within the SPP. The utility is listed as SPS. Recent news coverage suggests growing interest in renewable energy projects in the region.
Generated from interconnection queue and public data sources
State
NM
County
Lovington
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Hobbs - Yoakum 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-ERAS-2025-020