Project SPP-ERAS-2025-026 — Project Summary

Queue ID
SPP-ERAS-2025-026
Capacity
744 MW
Technology
Gas
Status
active
Location
Lawton, OK
Region
SPP
Developer
IA Status

SPP-ERAS-2025-026

SPP-ERAS-2025-026BetaActiveThermal / Combined CycleSPPLive · SPP

744 MW generation in Lawton, OK · In queue since October 2025

744 MW

Capacity

0

Components

7 months

In Queue

IA Status

Interconnection

Total Duration

7 months

Pre-Study0%
Queue EntryOct 2, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-ERAS-2025-026 is a proposed 744 MW gas-fired generation project located in Lawton, Oklahoma. The project, which utilizes thermal combined cycle technology, is being developed within the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-ERAS-2025-026. The interconnecting utility is AEP.

The project entered the SPP queue on October 2, 2025. It is currently listed as active in the queue, seeking ER/NR service and planning to interconnect at the Oklaunion-Lawton East Side 345kV Line.

Generated from interconnection queue and public data sources

Project Details

State

OK

County

Lawton

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Oklaunion-Lawton East Side 345kV Line

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP South Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-ERAS-2025-026