SPP-GEN-2001-036
80 MW generation in Quay, NM · In queue since January 1970 · Proposed COD December 2004
80 MW
Capacity
1
Components
Wind
56y 4m
In Queue
Operational
IA Status
Signed Jan 1970
Queue → IA
<1 month
IA → COD
34y 11m
Total Duration
<1 month
Schedule
260 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2004-12-31
SPP-GEN-2001-036 is a proposed wind generation project with a total capacity of 80 MW. The project is located in Quay County, New Mexico, and falls within the Southwest Power Pool (SPP) service area, with Southwestern Public Service (SPS) as the interconnecting utility. The point of interconnection is the Norton 115kV Switching Station.
The project entered the SPP interconnection queue on January 1, 1970, with a proposed commercial operation date of December 31, 2004. Its interconnection agreement (IA) is listed as Operational, with an IA date of January 1, 1970. The project is currently listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
NM
County
Quay
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Norton 115kV Switching Station
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Norton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.