SPP-GEN-2009-067S
20 MW generation in Eddy, NM · In queue since December 2009
20 MW
Capacity
1
Components
Solar
16y 5m
In Queue
Withdrawn
IA Status
Total Duration
16y 5m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2009-067S is a proposed solar generation project with a total capacity of 20 MW, located in Eddy County, New Mexico. The project is interconnected within the Southwest Power Pool (SPP) queue, with Southwestern Public Service (SPS) as the interconnecting utility. The project entered the queue on December 30, 2009.
The interconnection agreement (IA) status for SPP-GEN-2009-067S is currently listed as Withdrawn. The point of interconnection (POI) is the Seven Rivers 69kV substation.
Generated from interconnection queue and public data sources
State
NM
County
Eddy
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Seven Rivers 69kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Seven Rivers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2009-067S