SPP-GEN-2011-016
200.1 MW generation in Hodgeman, KS · In queue since March 2011 · Proposed COD December 2017
200.1 MW
Capacity
1
Components
Wind
15y 2m
In Queue
Withdrawn
IA Status
COD target: 2017
Total Duration
6y 9m
Schedule
103 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2017-12-01
SPP-GEN-2011-016 is a proposed wind generation project with a total capacity of 200.1 MW. The project is located in Hodgeman County, Kansas, and falls within the Southwest Power Pool (SPP) service area. The project's interconnection request was entered into the SPP queue on March 31, 2011, with an original proposed commercial operation date of December 1, 2017.
The interconnection agreement (IA) for SPP-GEN-2011-016 has been withdrawn. The point of interconnection (POI) is the Clark County-Spearville Ckt 2 345kV. The utility associated with the project is Sunflower Electric Power Corporation (SUNC).
Generated from interconnection queue and public data sources
State
KS
County
Hodgeman
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
—
Point of Interconnection
Clark County-Spearville Ckt 2 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2011-016