SPP-GEN-2011-049
250.7 MW generation in Beckham, OK · In queue since September 2011 · Proposed COD July 2020
250.7 MW
Capacity
1
Components
Wind
14y 8m
In Queue
Withdrawn
IA Status
COD target: 2020
Total Duration
8y 10m
Schedule
70 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-07-31
SPP-GEN-2011-049 is a proposed wind generation project with a total capacity of 250.7 MW. The project is located in Beckham County, Oklahoma, and falls within the Southwest Power Pool (SPP) service area. The interconnection customer is Oklahoma Gas & Electric (OGE). The project entered the SPP interconnection queue on September 30, 2011, with a proposed commercial operation date of July 31, 2020.
The interconnection agreement (IA) status for SPP-GEN-2011-049 is listed as Withdrawn. The point of interconnection (POI) is the Border 345kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OK
County
Beckham
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
—
Point of Interconnection
Border 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Border Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2011-049