SPP-GEN-2013-014
25.5 MW generation in Webster, NE · In queue since March 2013 · Proposed COD December 2015
25.5 MW
Capacity
1
Components
Wind
13y 2m
In Queue
Withdrawn
IA Status
COD target: 2015
Total Duration
2y 9m
Schedule
126 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2015-12-30
SPP-GEN-2013-014 is a proposed wind generation project with a total capacity of 25.5 MW. The project is located in Webster County, Nebraska, and is in the Southwest Power Pool (SPP) interconnection queue. The queue entry date is March 29, 2013, and the proposed commercial operation date was December 30, 2015. The interconnecting utility is Nebraska Public Power District (NPPD).
The interconnection agreement (IA) status for SPP-GEN-2013-014 is listed as Withdrawn. The point of interconnection (POI) is the Tap Guide Rock - Pauline (GEN-2008-123N Tap) 115kV.
Generated from interconnection queue and public data sources
State
NE
County
Webster
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
Tap Guide Rock - Pauline (GEN-2008-123N Tap) 115kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.