SPP-GEN-2015-029
161 MW generation in Dewey, OK · In queue since March 2015 · Proposed COD December 2020
161 MW
Capacity
1
Components
Wind
11y 2m
In Queue
Withdrawn
IA Status
COD target: 2020
Total Duration
5y 9m
Schedule
66 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-12-01
SPP-GEN-2015-029 is a proposed 161 MW wind generation project located in Dewey County, Oklahoma. The project, which interconnects to Oklahoma Gas & Electric (OGE) via the Tatonga 345kV point of interconnection, entered the Southwest Power Pool (SPP) interconnection queue on March 31, 2015. The proposed commercial operation date was December 1, 2020.
The interconnection agreement (IA) status for SPP-GEN-2015-029 is listed as Withdrawn. The project remains active in the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Dewey
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
—
Point of Interconnection
Tatonga 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Tatonga Substation