SPP-GEN-2015-055
40 MW generation in Beckham, OK · In queue since October 2015 · Proposed COD December 2024
40 MW
Capacity
1
Components
Solar
10y 7m
In Queue
Withdrawn
IA Status
COD target: 2024
Total Duration
9y 2m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
SPP-GEN-2015-055 is a proposed 40 MW solar generation project located in Beckham County, Oklahoma. The project, under consideration in the Southwest Power Pool (SPP) interconnection queue, is being developed by Western Farmers Electric Cooperative (WFEC). The project entered the queue on October 6, 2015, with a proposed commercial operation date of December 1, 2024. The point of interconnection is the Erick 138kV Substation.
The interconnection agreement (IA) status for SPP-GEN-2015-055 is currently listed as Withdrawn.
Generated from interconnection queue and public data sources
State
OK
County
Beckham
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
—
Point of Interconnection
Erick 138kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.