SPP-GEN-2015-056
101.2 MW generation in Roosevelt, NM · In queue since October 2015 · Proposed COD December 2020
101.2 MW
Capacity
1
Components
Other
10y 7m
In Queue
Withdrawn
IA Status
COD target: 2020
Total Duration
5y 2m
Schedule
66 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-12-01
SPP-GEN-2015-056 is a proposed generation project with a total capacity of 101.2 MW, located in Roosevelt County, New Mexico. The project, which utilizes an unspecified "Other" technology, is in the Southwest Power Pool (SPP) interconnection queue, with queue entry date of October 6, 2015. The proposed commercial operation date was December 1, 2020.
The interconnection agreement (IA) status for SPP-GEN-2015-056 is listed as "Withdrawn". The point of interconnection (POI) is the Eddy County-Tolk (Crossroads) 345kV substation. The project's transmission provider is Southwestern Public Service (SPS).
Generated from interconnection queue and public data sources
State
NM
County
Roosevelt
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Eddy County-Tolk (Crossroads) 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EDDY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.