SPP-GEN-2015-093
250 MW generation in Caddo, OK · In queue since September 2015 · Proposed COD December 2025
250 MW
Capacity
1
Components
Wind
10y 8m
In Queue
Withdrawn
IA Status
COD target: 2025
Total Duration
10y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
SPP-GEN-2015-093 is a proposed wind generation project with a total capacity of 250 MW. The project is located in Caddo County, Oklahoma, and interconnects to the Southwest Power Pool (SPP) via the Gracemont 345kV point of interconnection.
The project entered the SPP interconnection queue on September 29, 2015, with a proposed commercial operation date of December 31, 2025. Its interconnection agreement (IA) status is currently listed as withdrawn. The designated utility for the project is Oklahoma Gas & Electric (OGE).
Generated from interconnection queue and public data sources
State
OK
County
Caddo
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
—
Point of Interconnection
Gracemont 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2015-093