SPP-GEN-2016-088
151.2 MW generation in Dekalb, MO · In queue since August 2016 · Proposed COD October 2021
151.2 MW
Capacity
1
Components
Wind
9y 9m
In Queue
Withdrawn
IA Status
COD target: 2021
Total Duration
5y 2m
Schedule
55 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2021-10-29
SPP-GEN-2016-088 is a proposed wind generation project with a total capacity of 151.2 MW. The project is located in Dekalb County, Missouri, and interconnects within the Southwest Power Pool (SPP) region to the Kansas City Power & Light (KCPL) utility. The project entered the SPP interconnection queue on August 11, 2016, and initially proposed a commercial operation date of October 29, 2021.
The interconnection agreement (IA) status for SPP-GEN-2016-088 is listed as Withdrawn. The point of interconnection (POI) is the Mullen Creek-Sibley (Ketchum) 345kV line.
Generated from interconnection queue and public data sources
State
MO
County
Dekalb
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
KCPL
Entity
SPP
Service Type
—
Point of Interconnection
Mullen Creek-Sibley (Ketchum) 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2016-088