SPP-GEN-2017-048
300 MW generation in Williams, ND · In queue since May 2017 · Proposed COD December 2026
300 MW
Capacity
1
Components
Wind
9 years
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-31
SPP-GEN-2017-048 is a proposed wind generation project with a total capacity of 300 MW. The project is located in Williams County, North Dakota, and is being developed within the Southwest Power Pool (SPP) region. The interconnection customer is Basin Electric Power Cooperative (BEPC).
The project entered the SPP interconnection queue on May 31, 2017, with a proposed commercial operation date of December 31, 2026. The interconnection agreement for the project has been executed. The point of interconnection is the Neset 230 kV Substation.
Generated from interconnection queue and public data sources
State
ND
County
Williams
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
BEPC
Entity
SPP
Service Type
—
Point of Interconnection
Neset 230 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Neset Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.