SPP-GEN-2017-167
52 MW storage in Carter, OK · In queue since November 2017 · Proposed COD December 2027
52 MW
Capacity
1
Components
Battery
8y 6m
In Queue
Withdrawn
IA Status
COD target: 2027
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
SPP-GEN-2017-167 is a proposed 52 MW battery storage project located in Carter County, Oklahoma. The project is interconnected to the Southwest Power Pool (SPP) via the Sunnyside 345kV point of interconnection and is in the SPP interconnection queue as of November 29, 2017.
The proposed commercial operation date for the project is December 31, 2027. The interconnection agreement (IA) status for the project is currently listed as Withdrawn. The utility associated with the project is Oklahoma Gas & Electric (OGE).
Generated from interconnection queue and public data sources
State
OK
County
Carter
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
—
Point of Interconnection
Sunnyside 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Sunnyside Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2017-167