SPP-GEN-2020-012
113 MW hybrid in Jackson, OK · In queue since April 2020 · Proposed COD June 2027
113 MW
Capacity
1
Components
Solar
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
SPP-GEN-2020-012 is a proposed 113 MW hybrid solar and battery project located in Jackson County, Oklahoma. The project, which consists of 113 MW of solar capacity, is in the Southwest Power Pool (SPP) interconnection queue, under queue ID SPP-GEN-2020-012. The queue entry date is April 10, 2020, and the proposed commercial operation date is June 1, 2027. The interconnecting utility is AEP, and the project's point of interconnection (POI) is Snyder _x0013_ Altus Jct. 138kV. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
OK
County
Jackson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Snyder _x0013_ Altus Jct. 138kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2020-012