SPP-GEN-2020-067
352.5 MW generation in Terry, TX · In queue since April 2020 · Proposed COD December 2026
352.5 MW
Capacity
1
Components
Wind
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
SPP-GEN-2020-067 is a proposed wind generation project with a total capacity of 352.5 MW. The project is located in Terry County, Texas, and is interconnected within the Southwest Power Pool (SPP) region, under utility Southwestern Public Service (SPS). The project entered the SPP interconnection queue on April 24, 2020, and has a proposed commercial operation date of December 1, 2026.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Tuco to Yoakum 345kV line.
Generated from interconnection queue and public data sources
State
TX
County
Terry
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Tuco to Yoakum 345kV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.