SPP-GEN-2021-017
37.5 MW generation in Cloud, KS · In queue since April 2021 · Proposed COD December 2027
37.5 MW
Capacity
1
Components
Wind
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
SPP-GEN-2021-017 is a proposed wind generation project with a total capacity of 37.5 MW. The project is located in Cloud County, Kansas, and is being developed within the Southwest Power Pool (SPP) region. The project's interconnection request was entered into the SPP queue on April 30, 2021, with a proposed commercial operation date of December 31, 2027. The Interconnection Customer is ITCGP. The project's interconnection point is the Elm Creek 345 kV interconnection substation, and its current interconnection status is System Impact Study.
The proposed project consists solely of wind generation, with a total capacity of 37.5 MW.
Generated from interconnection queue and public data sources
State
KS
County
Cloud
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
ITCGP
Entity
SPP
Service Type
—
Point of Interconnection
Elm Creek 345 kV interconnection substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Plains Interconnection
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2021-017