SPP-GEN-2021-030
510.3 MW generation in Linn, KS · In queue since May 2021 · Proposed COD December 2026
510.3 MW
Capacity
1
Components
Solar
5 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
SPP-GEN-2021-030 is a proposed solar generation project with a total capacity of 510.3 MW. The project is located in Linn County, Kansas, and is interconnected within the Southwest Power Pool (SPP) region, with Kansas City Power & Light (KCPL) as the utility. The project entered the SPP interconnection queue on May 14, 2021, and has a proposed commercial operation date of December 31, 2026.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is at the Evergy tap of the La Cygne to Stillwell 345 kV line.
Generated from interconnection queue and public data sources
State
KS
County
Linn
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
KCPL
Entity
SPP
Service Type
—
Point of Interconnection
Evergy Tap the La Cygne to Stillwel 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.