SPP-GEN-2021-038
200 MW storage in Titus, TX · In queue since April 2021 · Proposed COD May 2028
200 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-31
SPP-GEN-2021-038 is a proposed 200 MW battery storage project located in Titus County, Texas. Interconnecting to the Welsh 345kV Substation, the project is in the Southwest Power Pool (SPP) interconnection queue with an entry date of April 30, 2021. The proposed commercial operation date is May 31, 2028. The project's interconnection status is currently in the System Impact Study phase.
The development project is being proposed within the American Electric Power (AEP) utility service area. It consists solely of battery storage, with a total capacity of 200 MW. The project is currently listed as active within the SPP interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Titus
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Welsh 345kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CSWWELSH1
- POI Substation
- Welsh Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2021-038