SPP-GEN-2021-069
249.6 MW generation in Hodgeman, KS · In queue since April 2021 · Proposed COD December 2027
249.6 MW
Capacity
1
Components
Wind
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
SPP-GEN-2021-069 is a proposed wind generation project with a total capacity of 249.6 MW. The project is located in Hodgeman County, Kansas, and is within the Southwest Power Pool (SPP) service region. The project's queue entry date is April 26, 2021, with a proposed commercial operation date of December 1, 2027. The interconnection customer is SUNC.
The project's interconnection status is currently in the System Impact Study phase within the SPP interconnection queue. The point of interconnection (POI) is the SUNC Spearville - Holcomb 345kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
KS
County
Hodgeman
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
—
Point of Interconnection
SUNC Spearville - Holcomb 345kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.