SPP-GEN-2022-004
33 MW generation in Sedgwick, KS · In queue since May 2022 · Proposed COD October 2026
33 MW
Capacity
1
Components
Solar
4 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
SPP-GEN-2022-004 is a proposed 33 MW solar generation project located in Sedgwick County, Kansas. The project is interconnected within the Southwest Power Pool (SPP) queue, with a queue entry date of May 26, 2022. The proposed commercial operation date is October 31, 2026. The point of interconnection is the Murray Gill 138 kV Substation.
The project's interconnection status is currently in the System Impact Study phase. The utility is Western Resources (WERE). The project has appeared in the SPP interconnection queue and is listed as an active project.
Generated from interconnection queue and public data sources
State
KS
County
Sedgwick
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
—
Point of Interconnection
Murray Gill 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Murray Gill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.