SPP-GEN-2022-007
135 MW generation in Lyon, KS · In queue since May 2022 · Proposed COD October 2026
135 MW
Capacity
1
Components
Solar
4 years
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
SPP-GEN-2022-007 is a proposed solar generation project located in Lyon County, Kansas, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 135 MW, is being developed for Western Resources, Inc. (WERE). It consists of 135 MW of solar photovoltaic generation.
The project entered the SPP interconnection queue on May 26, 2022, and has a proposed commercial operation date of October 31, 2026. Its interconnection status is currently in the System Impact Study phase. The point of interconnection is the Lang - Reading 115 kV Transmission Line.
Generated from interconnection queue and public data sources
State
KS
County
Lyon
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
—
Point of Interconnection
Lang - Reading 115 kV Transmission Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.