SPP-GEN-2022-038
200 MW generation in Harrison, TX · In queue since June 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
3y 11m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
SPP-GEN-2022-038 is a proposed solar generation project with a total capacity of 200 MW, located in Harrison County, Texas. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of June 23, 2022, and a proposed commercial operation date of December 31, 2025. The interconnecting utility is AEP.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Longwood to Scottville 138 kV line.
Generated from interconnection queue and public data sources
State
TX
County
Harrison
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Longwood to Scottville 138 kV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.