SPP-GEN-2022-054
200 MW generation in Bourbon, KS · In queue since June 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
3y 11m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
SPP-GEN-2022-054 is a proposed 200 MW solar generation project located in Bourbon County, Kansas. The project, which consists of 200 MW of solar photovoltaic generation, is in the Southwest Power Pool (SPP) interconnection queue as of June 23, 2022, with a proposed commercial operation date of December 31, 2025.
The interconnection customer is NEET. As of the current queue status, the project is in the System Impact Study phase of the interconnection process. The point of interconnection is the Wolf Creek - Blackberry 345 kV Tap. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
KS
County
Bourbon
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NEET
Entity
SPP
Service Type
—
Point of Interconnection
Wolf Creek - Blackberry 345 kV Tap
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2022-054