SPP-GEN-2022-071
90.824 MW generation in Pittsburg, OK · In queue since August 2022 · Proposed COD February 2026
90.824 MW
Capacity
1
Components
Solar
3y 9m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 6m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-02
SPP-GEN-2022-071 is a proposed solar generation project with a total capacity of 90.82 MW, located in Pittsburg County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of August 12, 2022, and a proposed commercial operation date of February 2, 2026. The interconnecting utility is AEP.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Talawanda to Canadian River 138 kV Line Tap. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
OK
County
Pittsburg
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Talawanda to Canadian River 138 kV Line Tap
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2022-071