SPP-GEN-2022-073
300 MW storage in Clay, MO · In queue since September 2022 · Proposed COD December 2027
300 MW
Capacity
1
Components
Battery
3y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
SPP-GEN-2022-073 is a proposed 300 MW battery storage project located in Clay County, Missouri. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of September 2, 2022, and a proposed commercial operation date of December 31, 2027. The interconnecting utility is Kansas City Power and Light (KCPL).
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Nashua 161 kV Substation. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MO
County
Clay
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
KCPL
Entity
SPP
Service Type
—
Point of Interconnection
Nashua 161 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Nashua Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2022-073