SPP-GEN-2022-075
175 MW generation in Ellis, KS · In queue since September 2022 · Proposed COD November 2027
175 MW
Capacity
1
Components
Solar
3y 8m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-19
SPP-GEN-2022-075 is a proposed solar generation project with a total capacity of 175 MW. The project is located in Ellis County, Kansas, and is interconnected within the Southwest Power Pool (SPP) region. The project's queue entry date is September 2, 2022, and the proposed commercial operation date is November 19, 2027.
The interconnection customer is ITCGP. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is a tap on the Spearville - Post Rock 345kV line.
Generated from interconnection queue and public data sources
State
KS
County
Ellis
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
ITCGP
Entity
SPP
Service Type
—
Point of Interconnection
Tap on the Spearville - Post Rock 345kV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.