Project SPP-GEN-2022-100 — Project Summary

Queue ID
SPP-GEN-2022-100
Capacity
80 MW
Technology
Solar+Battery
Status
active
Location
Cooper, MO
Region
SPP
Developer
IA Status
System Impact Study

SPP-GEN-2022-100

SPP-GEN-2022-100BetaActiveSolarBatterySPPLBNL + Live

80 MW hybrid in Cooper, MO · In queue since March 2023 · Proposed COD October 2026

80 MW

Capacity

1

Components

Solar

3y 2m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection

Total Duration

3y 7m

Impact Study25%
Queue EntryMar 24, 2023

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-10-01

About

SPP-GEN-2022-100 is a proposed 80 MW hybrid Solar+Battery project in Cooper County, Missouri. The project, located within the Southwest Power Pool (SPP) region, consists of 80 MW of solar generation. The interconnection request was entered into the SPP queue on March 24, 2023, with a proposed commercial operation date of October 1, 2026. The interconnection point is the Overton - Sedalia East 161 kV Substation, and the project's interconnection status is currently in the System Impact Study phase.

The utility is Kansas City Power and Light (KCPL). The project is currently listed as active in the SPP interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

MO

County

Cooper

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

KCPL

Entity

SPP

Service Type

Point of Interconnection

Overton - Sedalia East 161 kV Substation

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
HIGH
POI Substation
Sedalia

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.