SPP-GEN-2022-104
113.078 MW generation in Bryan, OK · In queue since January 2023 · Proposed COD February 2026
113.078 MW
Capacity
1
Components
Solar
3y 4m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 1m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-02
SPP-GEN-2022-104 is a proposed solar generation project with a total capacity of 113.08 MW. The project is located in Bryan County, Oklahoma, and is being developed within the Southwest Power Pool (SPP) interconnection queue. The queue entry date is January 26, 2023, with a proposed commercial operation date of February 2, 2026. The interconnecting utility is Western Farmers Electric Cooperative (WFEC).
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Brown - South Coleman Junction 138kV line. The project has appeared in recent news coverage regarding renewable energy development in the SPP region.
Generated from interconnection queue and public data sources
State
OK
County
Bryan
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
—
Point of Interconnection
Brown - South Coleman Junction 138kV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Junction
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2022-104