SPP-GEN-2022-136
200 MW storage in Bryan, OK · In queue since February 2023 · Proposed COD December 2027
200 MW
Capacity
1
Components
Battery
3y 3m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
SPP-GEN-2022-136 is a proposed 200 MW battery storage project located in Bryan County, Oklahoma. The project, which consists entirely of battery storage, is being developed by Western Farmers Electric Cooperative (WFEC). It is currently in the Southwest Power Pool (SPP) interconnection queue with an entry date of February 21, 2023.
The project's proposed commercial operation date is December 31, 2027. Its interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Colbert 138 kV Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OK
County
Bryan
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
—
Point of Interconnection
Colbert 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Colbert Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2022-136