SPP-GEN-2022-144
200 MW storage in Jackson, MO · In queue since February 2023 · Proposed COD December 2027
200 MW
Capacity
1
Components
Battery
3y 3m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
SPP-GEN-2022-144 is a proposed 200 MW battery storage project located in Jackson County, Missouri. The project, which consists entirely of battery storage, is in the Southwest Power Pool (SPP) interconnection queue as of February 21, 2023. The proposed commercial operation date is December 31, 2027. The point of interconnection is the Blue Mills BESS 161kV Substation.
The project's interconnection status is currently in the System Impact Study phase. The utility associated with the project is KCPL.
Generated from interconnection queue and public data sources
State
MO
County
Jackson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
KCPL
Entity
SPP
Service Type
—
Point of Interconnection
Blue Mills BESS 161kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Blue Mills Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2022-144