SPP-GEN-2022-176
215 MW generation in Nowata, OK · In queue since February 2023 · Proposed COD October 2026
215 MW
Capacity
1
Components
Wind
3y 3m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
SPP-GEN-2022-176 is a proposed wind generation project located in Nowata County, Oklahoma, within the Southwest Power Pool (SPP) region. The development project, with a total capacity of 215 MW, is being proposed for interconnection to the Northeastern - Delaware 345 kV transmission line. The project entered the SPP interconnection queue on February 17, 2023, with a proposed commercial operation date of October 31, 2026.
The interconnection request is currently in the System Impact Study phase. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
OK
County
Nowata
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Northeastern - Delaware 345 kV transmission line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.