SPP-GEN-2023-015
330 MW generation in Finney, KS · In queue since October 2023 · Proposed COD September 2026
330 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
SPP-GEN-2023-015 is a proposed solar generation project with a total capacity of 330 MW. The project is located in Finney County, Kansas, and interconnects within the Southwest Power Pool (SPP) region to the Finney-Carpenter 345 KV line. The queue entry date is October 2, 2023, and the proposed commercial operation date is September 1, 2026. The interconnection status is currently in the System Impact Study phase.
The development project consists of 330 MW of solar generation. The Southwest Public Service Company (SPS) is the utility associated with the interconnection. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
KS
County
Finney
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Finney-Carpenter 345 KV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2023-015