SPP-GEN-2023-063
135 MW hybrid in Rogers, OK · In queue since October 2023 · Proposed COD December 2028
135 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
SPP-GEN-2023-063 is a proposed 135 MW hybrid Solar+Battery project located in Rogers County, Oklahoma. The project, which consists of 135 MW of solar capacity, is in the Southwest Power Pool (SPP) interconnection queue, under utility AEP, with queue entry date of October 2, 2023. The proposed commercial operation date is December 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Catoosa - Owasso 88th 138 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OK
County
Rogers
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Catoosa - Owasso 88th 138 kV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM