SPP-GEN-2023-064
200 MW hybrid in Le Flore, OK · In queue since October 2023 · Proposed COD December 2028
200 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
SPP-GEN-2023-064 is a proposed 200 MW hybrid solar and battery project located in Le Flore County, Oklahoma. The project, which consists of 200 MW of solar generation, is in the Southwest Power Pool (SPP) interconnection queue under the queue ID SPP-GEN-2023-064. The queue entry date is October 2, 2023, and the proposed commercial operation date is December 1, 2028. The project's interconnection status is currently in the System Impact Study phase.
The designated utility for the project is the Southwestern Power Administration (SWPA). The point of interconnection (POI) is the RS Kerr-Stigler 161 kV line.
Generated from interconnection queue and public data sources
State
OK
County
Le Flore
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SWPA
Entity
SPP
Service Type
—
Point of Interconnection
RS Kerr-Stigler 161 kV line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.