SPP-GEN-2023-069
100 MW hybrid in Atoka, OK · In queue since October 2023 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-17
SPP-GEN-2023-069 is a proposed 100 MW hybrid solar and battery project located in Atoka County, Oklahoma. The project, which consists of 100 MW of solar generation, is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 2, 2023. The proposed commercial operation date is December 17, 2027.
The project's interconnection status is currently in the System Impact Study phase. Western Farmers Electric Cooperative (WFEC) is listed as the utility. The point of interconnection is the Tupelo - Atoka 138 kV Line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OK
County
Atoka
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
—
Point of Interconnection
Tupelo - Atoka 138 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Atoka