SPP-GEN-2023-120
130 MW generation in Swisher, TX · In queue since October 2023 · Proposed COD December 2030
130 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
SPP-GEN-2023-120 is a proposed solar generation project with a total capacity of 130 MW. The project is located in Swisher County, Texas, and is interconnected within the Southwest Power Pool (SPP) region, with Southwestern Public Service (SPS) as the interconnecting utility.
The project entered the SPP interconnection queue on October 2, 2023, and has a proposed commercial operation date of December 31, 2030. Its interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
TX
County
Swisher
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Kress 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.