SPP-GEN-2023-170
150 MW storage in Chariton, MO · In queue since October 2023 · Proposed COD June 2028
150 MW
Capacity
1
Components
Battery
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
SPP-GEN-2023-170 is a proposed 150 MW battery storage project located in Chariton County, Missouri. The project, which consists of 150 MW of battery capacity, is in the Southwest Power Pool (SPP) interconnection queue. The queue entry date is October 2, 2023, and the proposed commercial operation date is June 1, 2028. The project's interconnection status is currently in the System Impact Study phase. Evergy is the utility associated with the project, and the point of interconnection is the Salisbury 161 kV Substation.
The development project is listed in the SPP queue under queue ID SPP-GEN-2023-170.
Generated from interconnection queue and public data sources
State
MO
County
Chariton
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
Evergy
Entity
SPP
Service Type
—
Point of Interconnection
Salisbury 161 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Salisbury Substation