SPP-GEN-2023-171
150 MW storage in Jackson, MO · In queue since October 2023 · Proposed COD June 2028
150 MW
Capacity
1
Components
Battery
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
SPP-GEN-2023-171 is a proposed 150 MW battery storage project located in Jackson County, Missouri. The project, which is in the Southwest Power Pool (SPP) interconnection queue, entered the queue on October 2, 2023, with a proposed commercial operation date of June 1, 2028. The interconnecting utility is INDN.
The project's interconnection status is currently in the System Impact Study phase. It is located at the Sub M 161 kV Substation.
Generated from interconnection queue and public data sources
State
MO
County
Jackson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
INDN
Entity
SPP
Service Type
—
Point of Interconnection
Sub M 161 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Sub T
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2023-171