SPP-GEN-2023-187
20 MW generation in Eddy, NM · In queue since October 2023 · Proposed COD August 2023
20 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Withdrawn
IA Status
COD target: 2023
Total Duration
2y 7m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-08-31
SPP-GEN-2023-187 is a proposed solar generation project located in Eddy County, New Mexico, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 20 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the Chevron Green 115 kV Substation, and the interconnecting utility is Southwestern Public Service (SPS).
The project entered the SPP interconnection queue on October 2, 2023, with a proposed commercial operation date of August 31, 2023. Its interconnection agreement (IA) status is currently listed as Withdrawn.
Generated from interconnection queue and public data sources
State
NM
County
Eddy
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Chevron Green 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2023-187