SPP-GEN-2023-204
953 MW generation in Morris, TX · In queue since October 2023 · Proposed COD December 2028
953 MW
Capacity
1
Components
Gas
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
SPP-GEN-2023-204 is a proposed generation project located in Morris County, Texas, within the Southwest Power Pool (SPP) region. The development project, with a total capacity of 953 MW, consists of a gas-fired power generation facility. The project is listed in the SPP interconnection queue as of October 2, 2023, with a proposed commercial operation date of December 1, 2028. The interconnection request is currently in the System Impact Study phase.
The proposed project is interconnected to the AEP utility system at the Welsh-Lydia 345kV Line point of interconnection.
Generated from interconnection queue and public data sources
State
TX
County
Morris
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Welsh-Lydia 345kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.