SPP-GEN-2023-210
191 MW generation in Lincoln, OK · In queue since October 2023 · Proposed COD September 2026
191 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
SPP-GEN-2023-210 is a proposed solar generation project located in Lincoln County, Oklahoma. The project, with a total capacity of 191 MW, is being developed within the Southwest Power Pool (SPP) interconnection queue. The queue entry date is October 2, 2023, with a proposed commercial operation date of September 1, 2026.
The project is currently in the System Impact Study phase of the interconnection process. The interconnecting utility is Western Farmers Electric Cooperative (WFEC), and the point of interconnection (POI) is the Prague - Chernicky 138 kV Line. The project has appeared in recent news coverage regarding renewable energy development in the SPP region.
Generated from interconnection queue and public data sources
State
OK
County
Lincoln
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
—
Point of Interconnection
Prague - Chernicky 138 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2023-210